Customized UPDA MMUP Exam Courses 599 QAR | Xclusive Offer | Today Only

End in  . Register Now

Logo

Post Your Requirements

Buy with Confidence

Question 1

   RC cantilever wall is used to retain an engineer fill as shown. Drains are designed so that water pressure does not build up behind the wall. Which of the following patterns shows the correct placement of flexural reinforcement in the wall?

Question-Image
Correct Answer : b
Selected Answer : b
Explanation : uploads/Question_Image/37C1e.PNG
Explanation : Explanation-Image

Question 2

For the 2D rigid frame shown, the bending moment (k-ft)

Question-Image
Correct Answer : d
Selected Answer : d
Explanation : uploads/Question_Image/37C2e.PNG
Explanation : Explanation-Image

Question 3

   A trapezoidal channel has bottom width of 2ft a longitudinal slope of 0.5% and sides at 1V: 3H slopes as shown. Mannings n is 0.p2.if the depth of the flowing water is 2 ft the velocity is most nearly

Question-Image
Correct Answer : a
Selected Answer : d
Explanation : uploads/Question_Image/37C3e.PNG
Explanation : Explanation-Image

Question 4

A local municipality must make a determination about the feasibility of repairing the bridge. The estimated useful life of bridge is 25 years. The Marr is 8%. The relevant cost estimates are shown. All costs are shown in thousands of dollars

Question-Image
Correct Answer : d
Selected Answer : d
Explanation : uploads/Question_Image/37C4e.PNG
Explanation : Explanation-Image

Question 5

For the truss shown the member force k in member DI is most nearly

Question-Image
Correct Answer : c
Selected Answer : d
Explanation : uploads/Question_Image/37C5e.PNG
Explanation : Explanation-Image

Question 6

The concept of the ________ states that the changes related to one requirement scope, time, or cost will atleast influence one other element

Question-Image
Correct Answer : b
Selected Answer : b
Explanation :
Explanation : Explanation-Image

Question 7

You are in the process of contracting sellers to obtain bids and proposals. You found out that it might become a time consuming procedure to ensure that the sellers get a clear and common understanding of the procurement process and of the needs of your project. Which technique may help you save time?

Question-Image
Correct Answer : a
Selected Answer : a
Explanation :
Explanation : Explanation-Image

Question 8

For a project the following earned value data have been assessed. How much the value of work had been done?

Question-Image
Correct Answer : b
Selected Answer : b
Explanation :
Explanation : Explanation-Image

Question 9

A beam shown below. Which of the following represents the valid shape of bending moment diagram?

Question-Image
Correct Answer : d
Selected Answer : d
Explanation : in the first span load acting is point load hence inclined line,in the second span the load acting is udl hence parabolic curve
Explanation : Explanation-Image

Question 10

A parabolic vertical curve is being designed to connect two grades with 5% and followed by 3%. If PVC is at station 117+50.00 the elevation on the PVT is most nearly

Question-Image
Correct Answer : a
Selected Answer : c
Explanation : uploads/Question_Image/37C10e.PNG
Explanation : Explanation-Image

Question 11

   A highway with the straight alignment slopes down to a stop line as shown. The design speed of the highway is 45 mph. The SSD is most nearly

Question-Image
Correct Answer : a
Selected Answer : a
Explanation : uploads/Question_Image/37C11e.PNG
Explanation : Explanation-Image

Question 12

  A crane is used to lift a load of 16 tonnes as shown. The crane cabin has a ballasted weight of 24 tonnes. The allowable soil pressure is 2800 lb/Sq. Ft. If the crane is supported by 4 outriggers, the minimum contact area of the out trigeer pads is most nearly

Question-Image
Correct Answer : c
Selected Answer : c
Explanation : uploads/Question_Image/37C12e.PNG
Explanation : Explanation-Image

Question 13

In a steel plate with bolted connections the rupture of the net section is a mode of failure under

Question-Image
Correct Answer : a
Selected Answer : a
Explanation : tension will be dominant criteria for failure
Explanation : Explanation-Image

Question 14

In the bernoullis equation used in the pipe flow each term represents

Question-Image
Correct Answer : a
Selected Answer : a
Explanation :
Explanation : Explanation-Image

Question 15

Who should evaluate the performance of a quality improvement team leader?

Question-Image
Correct Answer : a
Selected Answer : a
Explanation :
Explanation : Explanation-Image

Question 16

During the course of project implementation any problems or issues that arise should be

Question-Image
Correct Answer : a
Selected Answer : a
Explanation :
Explanation : Explanation-Image

Question 17

In order for self directed teams to be successful the Role of the group leader must be that of

Question-Image
Correct Answer : a
Selected Answer : a
Explanation :
Explanation : Explanation-Image

Question 18

If the maximum moisture content is given to 17% and specific gravity of soil is given equal to 2.67 find the dry density according to the modified proctors test procedure

Question-Image
Correct Answer : c
Selected Answer : a
Explanation : uploads/Question_Image/37C18e.PNG
Explanation : Explanation-Image

Question 19

In the temporary structure in the referred picture if the soil is un drained stiff clay which one is correct?

Question-Image
Correct Answer : b
Selected Answer : b
Explanation : uploads/Question_Image/37C19e.PNG
Explanation : Explanation-Image

Question 20

Concrete curing shall be maintained above 50 Fahrenheit and in a moist condition for at least

Question-Image
Correct Answer : d
Selected Answer : d
Explanation : initial strength is taken as 7 days
Explanation : Explanation-Image

Question 21

Find the maximum BM on a beam with the length of 20 ft for the two 2000lb moving load with the distance of 4 ft.

Question-Image
Correct Answer : d
Selected Answer : b
Explanation : uploads/Question_Image/37C21e.PNG
Explanation : Explanation-Image

Question 22

  A 3hr storm over a 150 Sq. Km area produces a total runoff volume of 7*106cubic meter with a peak discharge of 360 cubic m / sec. What is the total excess precipitation?

Question-Image
Correct Answer : d
Selected Answer : b
Explanation : uploads/Question_Image/37C22e.PNG
Explanation : Explanation-Image

Question 23

   For the scaffolding estimate the axial force in the bracings

Question-Image
Correct Answer : b
Selected Answer : d
Explanation : uploads/Question_Image/37C23e.PNG
Explanation : Explanation-Image

Question 24

First operation during the detailed survey of Hill Road is,

Question-Image
Correct Answer : d
Selected Answer : d
Explanation : firstprocessnin detailed survey wii be fixing the BM
Explanation : Explanation-Image

Question 25

   A 2g storm over a 111 Sq. Km area produces a total runoff volume of 4*10^6 cubic meter with a peak discharge of 260 cubic meter /sec. What is the total excess precipitation?

Question-Image
Correct Answer : c
Selected Answer : b
Explanation : uploads/Question_Image/37C25e.PNG
Explanation : Explanation-Image

Question 26

In the activity network below what is the total float of task 5?

Question-Image
Correct Answer : a
Selected Answer : a
Explanation : uploads/Question_Image/37C26e.PNG
Explanation : Explanation-Image
Hi, How can i help you?
X

Our customer support team is here to answer your questions.

Ask us anything!

Send