End in . Register Now
Free Consultation
+974-77290171
Please enter your email.
Invalid email address.
Post Your Requirements
Teach On SkillXplore
[email protected]
If you already have an account with us, please login at the login page.
Please Fill All Details
{{add_user_message_success}}
{{add_user_message_error}}
Please enter your first name.
Please enter your last name.
{{user_details_message}}
Please enter your password.
The password must have 6+characters.
Please enter confirm password.
Password does't match with confirm password
{{login_user_message_error}}
For the refund, you can raise your queries to [email protected]
Question 1
A planned tunnelling project is expected to take approximately 4000 hrs to complete. The owner is not in rush to complete construction. Given this information the best of the proposed work schedule is
Question 2
A four lane free way runs through rural areas. Each lane is 11 ft wide. A recent traffic study for the directional weakday volume is 2400 vph in one direction. An average of 750 vehicles passes by during the busiest 15 mins. What is most nearly the peak hour factor?
Question 3
In a simply supported beam subjected to uniformly distributed load throughout the length, at which points is the stress due to {I} Flexure and {II} Shear equal to zero respectively. 1. At support section at neutral fiber 2. At mid span section at neutral fiber 3. At mid span section at top fiber 4. At support section at bottom fiber Which the above statements is / are correct ?
Question 4
An unsignalized T intersection has three legs are each two way. What is most nearly the total number of conflict point including crossing, merging, and diverging
Question 5
A planimeter recorded the areas enclosed by the 700 ft and 707 ft grading contours as 1200 ft^2 and 1800 ft^2 respectively. The volume of material enclosed by the contour lines is most nearly
Question 6
A project is typically defined in terms of scope time cost and which other parameters?
Question 7
Project reporting can best be defined as
Question 8
An internal quality audit should be designed primarily to answer which of the following questions?
Question 9
Which one of the following is added during the final stage of 15 pieces of equipment, 50 people, 400days productionof Portland cement?
Question 10
Bitumen is derived from
Question 11
whichof the following elements of a pitched roof industrial steel building primarily resists lateral load parallel to the ridge?
Question 12
Two circular footings of diameter D1 and D2bare resting on the surface of the same purely cohesive soil. The ratio of their gross ultimate bearing capacities is
Question 13
If an isolated footing with an area 2.25 m² is needed to carry a 0.25 m x 0.8 m column. The best footing shape would be :-
Question 14
The highest element in the hierarchical breakdown structure of the WBS is :
Question 15
An assembly made of a rigid arm A − B − C at end A and supported by an elastic rope C − D at end C is shown in the figure. The members may be assumed to be weightless at the lengths of the respective members as shown in the figure.
Question 16
A room is 35 ft x 25 ft in plan Ceiling height is 14 ft. Openings for doors and windows total 85 ft. The following data is given for plastering and painting operations. Plaster and paint crew: 1 supervisor $30/lrPlastering productivity 50 ft/LH. 1 labourer $12/lr Painting productivity = 150 f/LH. 2 painter $18/hrTheestimatedlabour cost for plastering and painting the room (walls and ceiling) is most nearly
Question 17
A cantilever retaining wall is shown below. The resultant active earth pressure per unit length (lb/f| of the wall is most nearly:
Question 18
A 20-8-wide 24-8-deep trench in a clayey soil is braced as shown below longitudinal spacing of the struts is 8 ft. The asial load in stu S, (k) is most nearly
Question 19
A 3-axle vehicle has a front axle load of 10 k, a drive axle of 28 k, and a rear (trailer) axle of 30 k, as shown below. The maximum bending moment (k-ft) produced by this truck on a 70-ft, simple span is most nearly:
Question 20
For the plane truss loaded as shown below, the force (k) in member CJ is most nearly:
Question 21
A concrete mix that has a tendency to bleed excessively can be provided by ?
Question 22
The activity on a node diagram for a project is shown below. All durations are in weeks. All relationships are finish to start uless noted otherwise. The free float (weeks) of activity A is:
Question 23
A contract has 90 days remaining until completion.Early completion will be paid $18,000 bonus per day that the duration is shortened. Activities on the critical path are targeted for "crashing" Critical activities can be accelerated by allocating additional crew wits. Additional cost and schedule reduction are shown in the table below. If crews must be added as a complete unit, the net bonus is maximized by the addition of how many crews?
Question 24
Question 25
What is the primary use of fast track scheduling ?
Question 26
The ratio of maximum water demand to average water demand is called :
Our customer support team is here to answer your questions. Ask us anything!
Mobile No: +974-77290171