Question 21
The tasks within a project, and their duration and cost data are shown below. Both normal completion time and crashed completion time (by allocating additional resources) are shown in the table.The activity on arrow representation of the project is also shown
For every week of early completion, the bonus is $1,000, and for every week that the project is late, the penalty is $800. If the revised target completion time is 9 weeks, the net cost for completing the project is most nearly: